It is acceptable to weigh the raw material (RM) in advance of the scheduled date of production.
However, the firm should be able to demonstrate that the materials and design of the containers in which the
RM are weighed and kept will not alter their quality, the characteristics of the RM must also be taken into
consideration. Interpretation 2 of Section C.02.026 Samples may provide guidance to this effect. Pre-weighed
material should be appropriately labelled to ensure traceability. A system should be in place to ensure that
the material is still suitable for use on the date of manufacturing.