If a contract manufacturer needs to change the raw material supplier, may the contract manufacturer make the change and simply notify the contract giver?
No, section 16.16 reads: “Changes in the process, equipment, test methods, specifications, or
other contractual requirements should not be made unless the contract giver is informed and
approves the changes.”