What are the expectations for qualifying equipment? For instance, does the OQ need to go to the limit that the piece of equipment is capable of running, or can it just go to the typical operating conditions, i.e., temperature, pressure, etc.?
Section 12.3 defines Operational Qualification (OQ) as documented verification that the
equipment or systems, as installed or modified, perform as intended throughout the anticipated
operating ranges.