As a minimum, a complete analysis should be performed at appropriate intervals and compared
to the certificate of analysis. The basic intent here would be verifying all the test results reported
on that Certificate of Analysis. But Q7A is a guidance document and alternatives may be
appropriate. If there are some parameters on the Certificate of Analysis that are not critical to
your use of the material and you chose not to analyze those, you should provide justification.